With or without a permit?

As a garden contractor, you are often asked to build swimming ponds, patios, greenhouses and more. But people often do not stop to consider whether a permit is required. Growers are also often unsure which projects require a permit. This article provides a brief overview of when and under what conditions you need to apply for a permit, and when you do not.
Permit exemptions
One of the basic principles of environmental planning law is that all urban development works require a permit. The Exemptions Decree, drawn up by the Flemish Government in 2010, provides an exception to this rule. Subject to certain conditions, urban development works are exempt from the permit requirement. However, many conditions apply. Here are some of them.
Applications for garden contractors
A patio, swimming pool or swimming pond is considered a hard surface. The client may lay hard surfaces without a permit up to a maximum of 80 m2, including all existing hard surfaces. Hard surfaces that are strictly necessary to access a building, for example, are exempt from the permit requirement. It is important to note that gravel and artificial grass are also considered hard surfaces.
A garden shed, greenhouse, garage or pool house may also be built next to a correctly permitted dwelling, provided the maximum area is 40 m2, including all existing outbuildings. Under certain conditions, it is also possible to add a hobby horse stable, subject to a permit.
Gates and fences up to two metres high are also exempt from the permit requirement. One exception is that solid fences in front gardens are exempt only up to a maximum height of one metre.
The installation of various small garden structures, such as garden ornaments, letterboxes, barbecues and play equipment, is exempt from the permit requirement.
The exemptions listed above apply only when the works are carried out within a radius of thirty metres of a building that is mainly permitted or deemed permitted. In addition, there must be no change of use requiring a permit, and the number of dwellings must remain unchanged. The exempt works are not permitted in spatially vulnerable areas.
Applications for growers
For growers, structures used to cultivate or protect agricultural crops, such as hail nets, are exempt from the permit requirement. Hail cannons, glass structures and buildings are exceptions and are not exempt. Permanent structures that remain in place after cultivation, such as covers used to protect strawberry crops, also require a permit. Structures removed after harvesting do not require a permit.
Silage clamps, for example for storing green waste, are also exempt from the permit requirement. Please note: an environmental permit must still be applied for, but only for the environmental section; no urban planning section is required. To qualify for this exemption, the structures must be built within a radius of fifty metres of a building complex, and no discharge to the public sewer may be provided for.
Other applications
Felling trees requires a permit in many cases. No permit is needed only within woodland areas, where replanting is to be expected. Outside woodland areas, felling a tree in a non-forested area is subject to a permit. Felling a solitary tree in a residential, agricultural or industrial area also always requires a permit, unless it stands less than fifteen metres from a dwelling.
Significantly altering the ground level also requires a permit. Previously, there was a fixed threshold: any raising or excavation of more than fifty centimetres required a permit. This has now been replaced by a qualitative criterion: any raising or excavation that is ‘significant’ requires a permit. The impact of the work on the site must be taken into account.
The municipality may also have its own rules on permit requirements. For example, it may impose additional conditions or extend the permit requirement through an urban planning regulation, an RUP or a BPA. To avoid problems, it is best to check with your municipality’s environmental department.
Consequences of an unauthorised structure
If you have built a structure that falls under the Exemptions Decree, there is no problem. However, building an unauthorised structure that does not qualify for an exemption, such as an outbuilding larger than 40 m² or non-essential hard surfacing covering more than 80 m², can cause problems.
When an application is made for a building permit, the city or municipality automatically checks the site’s permit status. If there are structures that breach the rules, this may make a later permit application
more difficult.
A particular structure may also cause a nuisance to a third party, such as a neighbour. The neighbour can then file a complaint. If the structure is unauthorised, you may find building inspectors on your doorstep. Building inspectors may also come across the breach by chance. In these cases, the owner will be warned to remove the structure. If they do not, a penalty may follow, in the form of an administrative fine or criminal prosecution by the public prosecutor’s office.
So always check whether or not the structure is exempt, because a properly permitted structure has nothing but advantages, for you and your client alike. DLV, as a consultancy and advisory firm, is always on hand to help with
your permit application.