Procedure and timescale for an environmental permit

In most cases, you need an environmental permit before you can start your project. This article therefore gives you an overview of the various steps involved in obtaining an environmental permit.
This subject may seem dull and repetitive, but this overview will help you form an accurate idea of what to expect when you need an environmental permit. Make the most of it.
When a permit is required
The environmental permit replaces the former building permit, environmental permit, land subdivision permit… Whether you want to put up a shelter or construct an entirely new building, the environmental permit regulations apply in both cases. The scale of the project makes no difference. The regulations state the following:
“No one may carry out urban development works without first obtaining an environmental permit to:
• erect or place a structure;
• bring materials together in a functional way to create a structure;
• demolish, rebuild, alter or extend a structure;
• …”
There are, of course, exceptions. Very small-scale projects, such as constructing a driveway, may be exempt. Make sure you check this. If no exemption applies, you need an environmental permit.
The various steps
The environmental permit application process involves several steps. The first and most important is preparing the application. During this stage, you find out which works require a permit, draw up plans with or without an architect, and provide justification for your application.
You then submit your application, starting an initial period of thirty days during which it must be declared complete and admissible. This is the time allowed to check that your application is complete. Have you forgotten something? Or is further information required? The procedure will then be suspended or you will be asked to provide additional information. Once the new information has been submitted, there is a further thirty days to check it.
As soon as your application is declared complete, its substantive assessment begins. This takes a maximum of 60 days for straightforward applications and a maximum of 105 or 120 days for other applications. You must receive a decision on your application within this period. These maximum time limits are very often used up, given the large number of permit applications.
A public inquiry may be held while your application is undergoing substantive assessment. During the inquiry, you must display a yellow public notice for thirty days. During this period, local residents can view the application and submit any objections. An objection does not automatically mean your application will be refused, but it does require extra attention!
During this period, external bodies are also asked to provide advice. The most common advisory bodies are the Department of Agriculture and Fisheries, the Watercourses Department, an intermunicipal heritage organisation, and the Agency for Nature and Forests. Companies such as Telenet and Fluvius may also be asked to provide advice.

If issues arise during the substantive assessment, such as an error, an objection or a negative opinion, the application plans may still be amended. This is done by submitting a request for changes, which allows you to amend or correct certain aspects of the application. A request for changes gives the authorities the right to extend the decision period by 60 days. The application period can also be extended by 60 days through an administrative loop if a procedural error has been made.
Finally, a decision must be made on your application within the time limit. It is assessed by the municipal executive of your municipality or by the provincial executive of your province. They decide on your application based on your documents, any objections and the advice received. They also receive a final recommendation from the chief official of the Environment Department, proposing whether or not to grant the permit.
The decision
Has a decision been made on your application? You must display it for a further 30 days in a clearly visible place along the public highway. The requirement to display the decision applies when a permit is granted, but usually also when an application is refused. During this period, interested parties have the opportunity to appeal. They have 35 days to do so, which is 5 days longer than the notice must be displayed. If no appeal is lodged, you may start work under your permit.
As a result, the process for a straightforward application takes around 30+60+35 days, excluding the preparation time, or approximately four months.
For other projects, the application takes around 30 +105+ 35 days, excluding the preparation time, or approximately five months.
In both cases, the process can also be extended by 60 days through a request for changes or an administrative loop.
Would you like help with your environmental permit application? Contact a DLV adviser at [email protected] or call the freephone number 0800 90 910.